Work Continues…
Posted by admin on 01 Jul 2009 | Tagged as: General
The lot has been cleared and Virgilio Inc has been hauling exceess material from the site for the past three weeks. The building site is now almost level. The well has been drilled and work will soon begin on the foundation. Pictures added this date.
Where did all that “dirt” go?
The Contractor (Fontaine Brothers) “owns “ the site. Including excavation and responsibility for the disposal of the excess material. The loam is piled on site to use as top cover for the final landscaping. the sand has to be tested to ascertain if it is suitable for fill around the foundation etc. The remainder had to be removed from the site and disposed of as fill. There is a rock crusher on site to handle the ledge that has been excavated.
The Town did retain the hardwood for use in the Town’s fuel assistance program.
No Comments
No comments yet.
RSS feed for comments on this post.
Sorry, the comment form is closed at this time.