On April 9, 2207, the Committee met with representatives from the Planning Board and discussed the process for obtaining Planning Board approval of the Plans. The site was discussed with the members who were very supportive of the proposed plan. The Planning Board agrees there does not seem to be any major obstacles for the project.

 Arrangements were made to keep the Planning Board advised of our progress. The Committee is very pleased with the expressed cooperation.

 The architectural firm of Caolo and Bieniek Associates has been hired by the Committee to conduct a peer review of the Needs Assessment and Feasibility Study completed by Kaestle Boos Associates, Inc.