Granby Public Safety Building Committee

Welcome!

The Town of Granby Public Safety Building Commitee would like to welcome you to our Web Log. We have designed this page to keep the members of the public informed as to the progress of the Public Safety Building project.

Tower installation

Posted by admin on 31 Jan 2010 | Tagged as: General

Employees from WPCS begin isntalltion of the radio tower at the Public Safety Complex last week.

 

 

Construction update

Posted by admin on 20 Jan 2010 | Tagged as: General

station

The Complex is now substanially “tight to the weather”. The sheetrock is up, windows are in , and the fire department garage doors have been  installed. All of the rough electrical in the office  side is complete and they have moved on to the fire bays.  They are also in the process of constructing the mezzanine in the fire apparatus bay.

Progress report….

Posted by admin on 20 Nov 2009 | Tagged as: General

The roo has been tar papered and is awaiting shingles. Rough electrical has begun.  The lot is due to receive a coat of pavement on Tuesday 11/24. Interior walls are mostly completed, and the concret floor in the apparatus bay has been poured. Some sheetrock has been installed.

Roof Trusses installed

Posted by admin on 23 Sep 2009 | Tagged as: General

trussses

Workers from Fontaine Brothers install roof trusses on the complex.  More photos in the “pictures” page.

We have walls…

Posted by admin on 10 Sep 2009 | Tagged as: General

walls

The contractors have started working on the walls of the station . The trusses are due September 22. We ae on schedule to be weather tight before the snow flies… the “hole” front fo the picture is an underground  water run off detention area.

New pictures added

Posted by admin on 20 Jul 2009 | Tagged as: General

See the “Pictures” page for photos of the latest progress.

Work Continues…

Posted by admin on 01 Jul 2009 | Tagged as: General

The lot has been cleared and Virgilio Inc has been hauling exceess material from the site for the past three weeks. The building site is now almost level. The well has been drilled and work will soon begin on the foundation. Pictures added this date.

Where did all that “dirt” go?

The Contractor (Fontaine Brothers) “owns “  the site. Including excavation and responsibility for the disposal of the excess material. The loam is piled on site to use as top cover for the final landscaping. the sand has to be tested to ascertain if it is suitable for fill around the foundation etc. The remainder had to be removed from the site and disposed of as fill.  There is a rock crusher on site to handle the ledge that has been excavated.

The Town did retain the hardwood for use in the Town’s fuel assistance program.

Groundbreaking Held

Posted by admin on 06 Jun 2009 | Tagged as: General

At 10 am on June 5, a brief ground breaking ceremony was held at Aldrich Field, the site of the new public safety complex. over 70 people attended the event and heard  speechs from Selectboard Chair Mary McDowell and former long–time Selectman Bryan Hauschild. Also in attendance were Fire Chief  Russ Anderson, Police Chief Louis Barry  and members from both Departments, as well as the members of the Building Committee a, other local officials and members of the public.

Groundbreaking Date Set

Posted by admin on 27 May 2009 | Tagged as: General

The PSBC voted Tuesday to hold the formal groundbreaking cermony on Friday June 5 at 10 AM.  Fontaine Brothers Inc. is the General contrarator on the project. They anticipate approximately one year to construct the facility.

The Board of Selectmen have voted a NO TRESPASS order on Aldrich Field for the duration of the project due to concerns over safety and security. It is anticipated that there will be a few “epen house” sessions during the construction process.

Hampshire Gazette Article on Building Project

Posted by admin on 20 Mar 2009 | Tagged as: General

The following is an atricle appearing in the Hampshire Gazette on the Public Safety Building Project:

Granby public safety building work set to start

By STEPHEN C. HILL
Staff Writer

Thursday, March 19, 2009
GRANBY - Construction of the $6.4 million combined police and fire station on Kellogg Field will start this spring.
James Trompke, chairman of the Public Safety Building Committee, said Fontaine Bros., of Springfield, has been hired to serve as the construction manager for the project.
Fontaine is now working with the project’s architect Kaestle Boos Associates to tweak the building’s design for what Trompke called “value engineering.” The move is to make sure the project can be done within budget, he said.
“The idea is to be complete and out to bid next month,” Trompke said.
“It’s a good environment to be seeking bids.”
A request for bids for the foundation and site work will be issued first, with other subcontracting bids following a week or two later, said Trompke.
Crews can be expected to break ground on the 11-acre site at the corner of State Street and North Street by the beginning of May, he said.
The committee has received permission from the state to use a process called cost management at risk. It allows construction to begin before the design and engineering is completed and it becomes the construction management company’s responsibility to bring the project in on budget, Trompke said.
The potential for major design changes during construction is minimized by the construction management company working closely with the architect, Trompke said.

Next »

Powered by WordPress